Government projects are vital to the citizens, who are the primary beneficiaries. Funded
projects seek to address socio-economic developmental challenges facing the
marginalized population. Therefore, such projects’ failure brings with it a profound
negative socio-economic impact to the project beneficiaries. Pretorius, Steyn, and Jordaan
(2012) report that fewer projects globally are completed within budget or meet original
goals and business objectives. The general objective of this study was to examine the
influence of project management practices in implementing county-funded road projects
in Uasin Gishu County in Kenya. Specifically, the study sought to establish the
relationship between project planning and implementation of county-funded road projects
in Uasin Gishu County, to assess the relationship between project team management and
implementation of county-funded road projects in Uasin Gishu County, to determine the
relationship between project monitoring and evaluation and implementation of county
funded road projects in Uasin Gishu County, to find out the relationship between project
stakeholder involvement and implementation of county-funded road projects in Uasin
Gishu County and to determine the moderating effect of government regulation on
implementation of county-funded road projects in Uasin Gishu County. The study was
guided by the Resource-Based View Theory, Goal Setting Theory and Institutional
Theory. The positivist philosophy was used to drive the study. The research used a
descriptive survey to establish conclusions about how project management practices
influence the delivery of county-funded road improvements in Uasin Gishu County. The
study was conducted in Uasin Gishu County in Kenya. According to the Uasin Gishu
County report (2023), there were a total of 250 employees in the management-level
positions under the Ministry of Roads and Public Works. The unit of analysis was
therefore County-Funded Road Projects in Uasin Gishu County, while the unit of
observation was 250 management employees. The research employed Taro Yamane’s
(1967) sample size calculation, assuming a 5% error term. The research picked 153 people
from a target sample of 250 employees. Employees who work on road construction in
Uasin-Gishu County make up the majority of this group. Thematic analysis was used to
analyse qualitative data, whereas descriptive and inferential statistics (Pearson correlation
coefficient, multiple regression analysis, and stepwise regression analysis) were used in
analysing quantitative data with the help of the SPSS statistical software. The study used
a 95% confidence level. Based on the findings, the study concluded that project planning
positively and significantly influences the implementation of county-funded road projects
in Uasin Gishu County. In addition, the study concluded that project team management
positively and significantly influences the implementation of county-funded road projects
in Uasin Gishu County. Further, the study concluded that project monitoring and
evaluation positively and significantly influences implementation of county-funded road
projects in Uasin Gishu County. The study also concluded that project stakeholder
involvement positively and significantly influences the implementation of county-funded
road projects in Uasin Gishu County. The study concludes that Government regulation
has a significant moderating effect on the influence of implementation of county-funded
xxiii
road projects in Uasin Gishu County. This study, therefore, recommended that the Uasin
Gishu County should prioritise project planning, project team management, project
monitoring and evaluation, and project stakeholder involvement. |