Abstract:
Variations are almost inevitable in construction projects and play important role in
determining the closing cost and time of the projects. In civil engineering construction
projects in Kenya, variations are incessant and excessive in magnitude. This study
therefore investigated the factors contributing to variation orders and their effects on
civil engineering construction projects in Kenya and proceeded to recommend an
effective variation order management system.
The study was conducted through survey method. Data was collected using a total of
95 questionnaires. The survey achieved a 78% rate of return. The data was analysed
using percentages, Relative Importance Index (RII), and Kendall’s coefficient of
concordance. The results were presented in tables and pie-chart diagrams.
The results suggest that in civil engineering construction projects in Kenya, the client
is the most predominant origin agent of variations at 55%, while additional work is
the most common aspect of variations at 58%. Using RII, the five most important
factors causing variation orders were found to be: delay in land
acquisition/compensation (0.859); differing site conditions (0.832); change of plans or
scope by client (0.762); change of schedule by the client (0.751); and lack of
coordination between overseas and local designers (0.741). In addition, the three most
important effects of variation orders were found to be: cost overruns (0.903);
contractual claims and disputes (0.814); and time overruns (0.811). The study also
established that there is no existing variation management system for civil
engineering construction projects in Kenya and consequently developed an effective
model that if adopted, would help reduce the occurrence of variations and ensure that
those that are inevitable do occur in a controlled manner.
To minimise the occurrence of variation orders in civil construction in Kenya, the
study recommended the following: conclusion of design before tendering; thorough
feasibility study; clear and precise project brief devoid of ambiguities; and proper
coordination between overseas and local designers.
The study concludes that the success of variation management depends not only on
the diligence of the client and consultant during the preconstruction stage but also
upon effective communication and collaboration between project team members
throughout the project life cycle.